SHOULD WE ANTICIPATE A FLOOD OF ADAPTATION LAWSUITS AND REFORMANTION, OF CONTRACTS? 13 April 2020
SHOULD WE ANTICIPATE A FLOOD OF ADAPTATION LAWSUITS AND REFORMANTION, OF CONTRACTS?

Many restrictive measures have been and are being taken both nationally and internationally in order to mitigate against the global “Coronavirus” (Covid-19) epidemic, which has been detected in almost all countries and continues to spread rapidly. Due to fact these restrictive measures impact commercial relations, business life and many contractual relationships directly, the status of these contracts and the legal relations between parties has started to be discussed and debated intensely.
These discussions and debates likely influence whether Coronavirus epidemic constitutes force majeure with respect to these contractual relationships, whether a failure by the parties to fulfill fully perform their contractual obligations due to the various national and international measures twill be considered a breach of their contract. In this context, we discuss below the subject of court adaptation or reformation of contractual obligations.
Before seeking a court adaptation of a contract, of course, , the parties are free to seek an agreement to amend their contracts to adapt to new circumstances, that is to agree to their own reformation without court intervention. If any such effort is unsuccessful, however, and certain conditions explained below exist, either party may request a judge to reform or adapt the contract to new circumstances, in other words, parties may file a lawsuit seeking to have the contract adapted or reformed.
Principles of “adherence to a contract (pacta sunt servanda)” and “freedom of contract” are cornerstones of Turkish contract law. As recognized by the Turkish Court of Appeal in well-established case-law, pursuant to these principles, the contract is to be performed according to its provisions at the time it was executed. In other words, even if new conditions arise making the performance of a party’s contractual obligations more difficult, the party is still obligated to perform as provided for in the contract, despite the new difficulties. In other words, the principle of adherence to a contract, as mentioned, constitutes one of the most fundamental principles of the law of contract, with the goal of providing predictability and certainty regarding the performance of contractual obligations, as well as encouraging the parties to act in good faith.This principle, however, is subject to certain limitations found in the private law.
The economic balance between the mutual performances existing when contract are executed may become unbalanced to the extent performance byone of the parties would result in a significant hardship for that party. In this case, abiding by the contract, and the principle of adherence to a contract, may result in unacceptable injustice or unfairness. In such a situation the principle of adherence to a contract gives way to the principle of “adapting the contract to changing circumstances”.
If changing circumstances circumvent the intent of a party or parties existing at the time a contract was executed, and the changes cause a situation strikingly and unpredictably unjust, the parties may be found to not be bound by the contract either wholly or in part. When faced with such changing circumstances, it may be necessary to seek reformation of the contract pursuant to Article 2 of the Turkish Civil Code.
Article 2 provides that in the case where extraordinary circumstances that: (i) were not reasonably foreseen, and were in fact not foreseen by parties at the time the contract was executed; and (ii) destroy the balance between mutual performances , making performance of contractual obligations by one or more of the parties significantly more difficult, provided the affected parties have not yet fulfilled the subject obligations or has fulfilled them with a reservation of rights, a judge may decide to require the performance in question for the benefit of the other party or may decide to excuse the affect parties from the obligations in question in full or in part and, in addition may reform or adapt the contract to take into consideration the extraordinary change of circumstances.
Adaptation lawsuits are most often seen in long-term, perpetual debt relationships. Adaptation in these situations, which is an exception of the principle of adherence to a contract, is addressed by Article 138 of the Turkish Code of Obligations under the title of "Hardship". According to this Article; “An extraordinary situation, which is not foreseen by the parties at the time of the contract and which was not anticipated by them, arises for a reason not due to the fault of the debtor and changes the existing facts at the time against the debtor in such a way as to violate the rules of good faith, then, if the debtor has not yet fulfilled his/her obligations due to the excessive difficulty of performance, the debtor shall have the right to request from the judge the adaptation of the contract to the new conditions and to revoke the contract if this is not possible. In contracts providing for continuing obligations, the debtor shall terminate the contract.”
One of the issues that need to be discussed given the current situation is possibility of bringing adaptation lawsuits, based on the “Coronavirus” (Covid-19) epidemic disease being an extraordinary situation a f unforeseen at the time contracts were signed by parties. For instance, “unpredictability” requirement for the adaptation of contracts signed before the virus had shown up in Turkey would be considered differently with regard tocontracts signed at the time the epidemic began to be seen in Turkey’s neighbouring countries in March 2020, and differently still when the virus started to be seen in Turkey. An argument that it was unforeseen by parties to a contract signed in, say, March 2020, when this epidemic had perhaps become the sole focus of the world, pushing even wars to the side, would not seem to be consistent with the requirement of good faith. We believe it likely experts would agree that the epidemic should be accepted as unforeseen for contracts signed prior to the time the virus showed up in Turkey or had become a global phenomenon.
To sum up, principles of “adherence to a contract” and “freedom of contract” are fundamental principles in Turkish law, pursuant to which a contract is to be performed as provided in it at the time it was executed, as has been settled by the case-law of the TurkishCourt of Appeal. That said, and although the measures imposed by the government have only covered a period of two to three months, if the, undeniably significant, effects of this epidemic continue, and even deepen, during this time and beyond, we expect experts will likely conclude these effects have deeply impacted the balance of the parties’ performances in long-term and perpetual contracts. For this reason, it may be that we will witness a flood of adaptation lawsuits in the upcoming weeks and months, assuming the other conditions set forth Article 138 of Turkish Code of Obligations and Article 2 of the Turkish Civil Code are present.
More particularly, for a judge to decide to adapt a contract due to “Coronavirus” (Covid-19), the following conditions must be satisfied:
- The balance between the performances of the parties to the contract should have become unbalanced to such an extent that one of the parties cannot be expected to perform some or all of its contractual obligations.
- The change in the balance between performances should arise from extraordinary reasons which were not and could not have been foreseen when contract was executed.
- The circumstances that cause the hardship should not be the fault of the party seeking adaption.
The party seeking adaptation should either not yet have fulfilled the obligation sought to be adapted or, if the party has fulfilled the obligation, it did so while reserving its rights given the excessive difficulty of the performance.
Other News
-
26.2.2021
WOMAN, BUSINESS AND LAW / 2021
We are proud to make a contribution on Women, Business and the Law 2021 report published by World Bank Group. It is the seventh in a series of reports that provide objective measures of legal and regulatory barriers to women’s entrepreneurship and employment in 190 economies. Amidst a global pandemic that threatens progress toward gender equality, the report identifies barriers to women’s economic participation and encourages reform of discriminatory laws. This year, the study also includes important findings on government responses to the COVID-19 crisis and pilot research related to childcare and women’s access to justice. The website allows for comparisons of the data at both the indicator and economy levels. https://lnkd.in/dUPCvjK
-
16.2.2021
What Are The Impact Of “Digital Inheritance” On Heritage And Inheritance?
Today, rapidly developing technology brings about change in all areas of law. Although our lives get easier with the development of new technologies, since the new concepts and institutions brought by technology have not been defined in the legal world, these concepts and institutions have been causing discussions.
-
9.1.2021
THE LIMITS OF UNFAIR COMPETITION BY DENIGRATING UNDER THE LIGHT OF THE JUDGEMENT OF THE GENERAL ASSEMBLY OF CIVIL CHAMBERS OF SUPREME COURT
-
4.1.2021
COMMUNIQUE ON THE PROCEDURES AND PRINCIPLES RELATING TO THE APPLICATION OF ARTICLE 376 OF THE TURKISH COMMERCIAL LAW NO 6102 HAS BEEN CHANGED!
-
24.12.2020
NEW REGULATION ON PROCESSING OF PERSONAL DATA IN ELECTRONIC COMMMUNICATIONS SECTOR PUBLISHED
-
23.12.2020
CLIENT ALERT FOR THE TURKISH COMPANIES ON RENEWABLE ENERGY SECTOR AND CURRENT ISSUES RELATED TO RENEWABLE ENERGY SECTOR IN UKRAINE
-
13.11.2020
WHAT IS THE MONETARY LIMIT REGARDING THE SIMPLIFIED PROCEDURE APPLIED IN COMMERCIAL CASES?
The monetary limit on commercial cases subject to the simplified trial procedure has been rearranged with the Law No. 7251, which entered into force on 28.07.2020. What does this amendment bring to our procedural law?
-
10.11.2020
AFTER SALES SERVICES REGULATION, INTRODUCTION AND USER MANUAL REGULATION AND WARRANTY CERTIFICATE REGULATION HAVE BEEN CHANGED
-
6.11.2020
THE PRELIMINARY INJUCTION AND PRECAUTIONARY ATTACHMENT WHICH ARE PRONOUNCED IN THE PRESENCE OF PARTIES
Is it possible to apply for an appeal within the framework of the new HMK against the preliminary injunction and precautionary attachment decisions which are pronounced in the presence? What has changed with the new HMK?
-
30.10.2020
WHAT ARE THE AMENDMENTS INTRODUCED REGARDING THE “SUBMISSION AND EVIDENTIALITY OF COMMERCIAL BOOKS?
-
23.10.2020
WHAT DOES THE NEW HMK SAY ABOUT "AMENDMENT OF PLEADING AFTER THE REVERSAL"?
A groundbreaking change has taken place that will put an end to the controversies that have been going on for decades regarding the "Amendment of Pleading After Reversal Decision" regulation of the HMK. In this newsletter, we are going to examine what the new regulation brings.
-
20.10.2020
THE GUIDELINE ON EXAMINATION OF DIGITAL DATA DURING ON-SITE INSPECTIONS IS PUBLISHED
-
16.10.2020
WHAT ARE THE CHANGES INTRODUCED REGARDING THE "EXTENSION AND CHANGE OF CLAIMS AND DEFENSE" IN THE CODE OF CIVIL PROCEDURE NUMBERED 6100 WITH THE LAW NO. 7251?
The amendments brought to the Code of Civil Procedure in terms of “the Extension and Change of the Claims and Defense” is examined with our newsletter this week.
-
15.10.2020
REVIEW ON THE DRAFT COMMUNIQUE ON REMOTE IDENTIFICATION METHODS TO BE USED BY BANKS
-
10.10.2020
WHICH AMENDMENTS HAVE BEEN MADE TO THE REGULATION RELATED TO THE PROCEDURES AND PRINCIPLES OF THE GENERAL ASSEMBLY MEETINGS OF JOINT STOCK COMPANIES?
A significant amendment has been made within the scope of The Regulation on the Amendment to the Regulation Related to the Procedures and Principles of the General Assembly Meetings of Joint Stock Companies and Representatives of the Ministry of Customs and Trade to Attend These Meetings published in the Official Gazette dated 09.10.2020 and numbered 31269. We will examine what the new regulation brings.